Record sidebar summarizing DEP agreement that will truck 30,000,000 pounds of contaminants back into the community of Lincolnville

Publication Date: 11/14/07


The following are details of the city's agreement with the Department of Environmental Protection


Remove the thousands of tons of lime sludge and street sweepings from the North Holmes borrow pit.


Remove within 475 days all dirt taken from the Riberia site and return it there.


Cover the returned dirt on the Riberia Street site with clean fill and vegetation within 60 days.


Turn over within 45 days all bills or manifests documenting the excavation and transportation of the fill to Riberia.


Give a report that, among other things, shows analysis of the soil and surface water on Holmes Boulevard, plus the results from three monitoring wells.