From State Affairs FL:

KEY POINTS
- Consumer groups asked the Florida Supreme Court to reject FPL's plan for supplying electricity to data centers
- Attorneys argued that FPL's plan fails to protect residents and businesses from costs
- The Public Service Commission has scheduled a May hearing to review the utility's plan
Consumer groups want the state Supreme Court to find that a Florida Power & Light plan for providing electricity to data centers does not adequately “insulate” residents and businesses from costs tied to the facilities.
Attorneys for the groups Florida Rising, the League of United Latin American Citizens and the Environmental Confederation of Southwest Florida argued in a brief last week that the plan fails to meet requirements of a new state law requiring data centers to cover their full electricity costs.
The plan includes “tariffs,” which detail issues such as rates and contract terms. The brief contends that tariffs would “squeeze FPL’s existing residential and small business customers so that data centers, developed by and/or for some of the planet’s wealthiest companies, can pay less. This flies in the face of the Florida Legislature’s unambiguous mandate that data centers must pay their actual costs.”
The groups, represented by attorneys from the Earthjustice legal organization, included the arguments in a broader legal challenge to an FPL rate settlementthat the Florida Public Service Commission approved last year. Tariffs for data centers were part of the settlement.
FPL and other utilities were required to file plans by Oct. 1 at the Public Service Commission to comply with the new data center law. FPL’s plan relies on the tariffs that were approved in the settlement.
An Oct. 1 FPL news release said the “company’s rate structure — approved last year — already satisfies the customer protection requirements established by Florida’s new data center law.”
The Public Service Commission has scheduled a May hearing on the plan. But the consumer groups argued in last week’s brief that the Supreme Court also should consider the plan in the settlement challenge.
The brief says the tariffs “violate Florida law because they do not reasonably ensure that the cost to serve large loads will not shift onto the general body of ratepayers,” adding that they “also do not establish rates that are fair, just, and reasonable.”
For example, the brief says FPL already has plans to build solar power facilities near potential data center sites in Palm Beach, Martin and St. Lucie counties. The groups contend it is “likely that the generation from these sites will go directly to powering data centers” and that “the general body of FPL ratepayers will be footing the bill.”
Florida has long had data centers, which house computer servers and other equipment and serve as a backbone for digital technology. But none are the hyperscale data centers that have spurred debate in Florida and across the country — and are in demand amid the artificial intelligence boom.
The law, Senate Bill 484, requires that each data center “bears its own full cost of service and that such cost is not shifted to the general body of ratepayers.” The plans filed by FPL and other utilities do not address specific data center projects, but FPL officials have said repeatedly that they expect to announce a data center deal before the end of the year.
In an Oct. 1 statement, FPL President and CEO Scott Bores said the tariffs in last year’s settlement comply with the law.
“Across the country we saw increasing demand from large energy users, and before any large data centers arrived in Florida, we worked to establish, and the PSC unanimously approved, one of the nation’s strongest customer-protection frameworks,” Bores said. “It ensures data centers and other large load customers pay their own way, including 100% of the power generation needed to serve them.”
In the first test of the law, the Public Service Commission on Nov. 3 rejected Duke Energy Florida’s plan. Commissioners said the plan did not ensure data centers would fully cover their electricity costs. Duke plans to file a revised plan.
Jim Saunders is the managing editor at State Affairs Florida. Reach him atjsaunders@stateaffairs.com or on X @JSaundersnews.